
|
|
|
|
|
General
Septic tanks and cess pools are designed in accordance with BS6297 and should be of watertight construction so
that they permit neither ingress of ground water or egress of sewage to the ground. They should be placed in a
suitable position, minimum 15 meters from dwelling with access provided to allow tank emptying vehicle to
operate within suction capability as it is advisable to empty septic tanks twice per year.
A diagram of Septic Tank arrangement can be viewed in Fig 1.
Cesspools and septic
tanks should be adequately ventilated and access to rod the horizontal inlet pipe should be provided. Calculation
of the total capacity of a septic tank should be made on the basis of the number of persons to be served. The
following formula is recommended for general use, where desludging is carried out at not more than 12 monthly
intervals.
C = (180P + 2000) where C is the capacity of the tank in litres, with a min of 2720 litres
P is the design population with a minimum of four persons
Therefore the capacity of tank for four persons = 4 x 180 + 2000 = 2720 litres (598 Gallon)
Therefore the capacity of tank for six persons = 6 x 180 + 2000 = 3080 litres (675 Gallon)
Note: Design populations is the no of persons permanently using the dwelling.
Capacity may be different for Sewage Treatment Plant.
A septic tank will perform two main functions
- Settlement Tank
Contains the crude sewage (solids) which should be emptied at least once per year (desludged), allow the
more refined liquid sewage to pass through for filtering.
- Filtering
The prime function of a filter is to seperate the remaining solids from the more refined liquids and to
introduce air (oxygen) to feed the bacteria which in turn will further purify the liquid before entering a stream
or waterway.
Depending on the type of soil surrounding a septic tank outlet, height of water table (ground water level) and
position of surrounding lakes or waterways, advice should be sought from your local authority as to which
type of filter is required.
Generally
- If low water table and where ground is rock, gravel or chalk there may be no seperate filter required other
than liquid dispersed into shallow gravel filled herring bone trenches with porus pipe. (Percolation Area)
- If low water table but ground is not as above then a stone filled (media) filter bed may be used, provided air
ventilation is allowed to flow freely through stones.
- Introduce air to liquid effluent by means of a compressor which may all be contained within the same
specially designed tank. (Small Sewage Treatment Plant) as per new European regulations which specify
Quality liquid should be at tank outlet.
Where water table or out fall drain is higher then outlet pipe and gravity flow is not possible, a submersable
pump would be required to empty septic tank.

Tracey Concrete Manufacturer 1800 square sections as can be seen in Fig 2
Tracey Concrete Manufacturer 1800 square sections as can be seen in Fig 3
Fitting Instructions
- Dig hole to required size and depth allowing
working room. This will vary depending on type of ground.
- Either use precast bases or insitu concrete making
sure they are placed level. As an alternative blocks
can be placed level in each corner for precast
sections to rest on and pour insitu concrete floor
later allowing concrete to undermine the walls of the sections.
- Using the lifting holes provided, sling each section into place, bedding each with 3:1 sand/cement as required between sections.
- Slide baffle slabs into position, making sure
knockout holes are furthest away from inlet pipe, break out knock holes on second baffle from top.
- Place all pipes, tipper, stones and asbestos.
- Place lids making sure they are turned correct way
for knock out holes.
- Grout around all pipes and lifting holes with 3:1 sand/cement mortar.
- Backfilling, if done immediately after placing should
be on either side to avoid pressure which may push septic tank out of place.
Note: Although each section is identical with knock
out holes, it is important to turn them the correct
way so knockout holes are in the proper position
for pipes.
|
|
|
|